Job completed for Rick E.
Completion date: November 2, 2026
Location: Chandler, OK
Solutions provided:
Installed a new 3/4” high-pressure gas line from the new gas meter to the existing underground gas yard line. Performed a pressure test on the yard line and the gas piping throughout the home in preparation for the city inspection.
The gas piping successfully passed the city inspection. Following approval, connected the home's gas line to the existing 1” regulator and tied it into the yard gas line.
Also installed a new 1” high-pressure gas line from the gas meter to the designated location for the future pool heater connection.
Team members on this project:
Dalton