Job completed for Lynea I.
Completion date: July 7, 2025
Location: Prague, OK
Solutions provided:
At the meter, installed the new meter union and ran 1 inch pex from the meter and tunnel under into the crawlspace. Installed the necessary sleeves. We had to run approximately 25 foot across the crawlspace before we got to the main service line at this point we installed the silcock and tied into the main line. Tested and no leaks
Team members on this project:
John